Public works cmte probes status of Mega Health Center project in Carmen

  • 1 hour ago
  • 1 min read

Acting on the endorsement of the committee on health, the committee on public works, chaired by Councilor Al Legaspi Sr., convened to look into the status of the ongoing construction of the Mega Health Center in Macanhan, Barangay Carmen.


During the meeting, the Local Finance Committee reported that ₱16,451,734.35 has been disbursed to the previous contractor, Nurben Engineering and Building Contractor.


This amount covers the 15% mobilization fee, as authorized under the Government Procurement Reform Act, as well as payment for the first partial billing equivalent to 15% of the project’s accomplishment.


Providing updates on the project’s implementation, Engr. Edgar Patriana of the City Engineer’s Office, disclosed that a Show Cause Order has already been issued to the contractor, and that the office is currently awaiting the formal receipt of the termination order.


He further noted that preparations are underway for the engagement of a new contractor, with assurance that available funds remain sufficient to support the continuation and completion of the infrastructure project.


In response to the request of council members, Engr. Patriana committed to submitting a comprehensive status report, including a proposed timeline for project completion, to guide the committee’s oversight and ensure its implementation. (SPE/SP)



 
 
 